ts
ts

Grid project Beznau – Birr

Swissgrid is expanding the existing line between Beznau and Birr to 380 kV. One section of the line will run underground in future. The 220 kilovolt line that passes through Neu-Riniken will be dismantled.

Your contact for this grid project

Jan Schenk

Overview

The existing 220-kilovolt Beznau – Birr line is part of the expansion programme between Beznau (AG) and Mettlen (LU). The line is a bottleneck in the Swiss transmission grid. To increase capacity, this entire line will be converted to a voltage of 380 kilovolts. The line will be partially laid underground in the Bözberg/Riniken area («Gäbihübel» region). The project consists of the 1,3-kilometre cable route, two transitional structures (connection between the underground line and the overhead line) as well as the 5,2-kilometre overhead line connections between Rüfenach and Schinznach.

Improvement compared to the current situation


Project

The project consists of the 1.3-kilometre cable route, two transitional structures (connection between the underground line and overhead line) as well as the 5.1-kilometre overhead line connections from pylon 20 in Rüfenach to pylon 30 in Krähtal to the northern transitional structure, as well as from the southern transitional structure to pylon 32 in Villnachern to pylon 37 (237) in Schinznach.

The northern transitional structure will be constructed in Pfaffenfirst in the municipality of Riniken. The transitional structure will be used to connect the underground cable to the overhead line and is about the size of an ice hockey rink. A small amount of permanent forest clearance and suppression of forest growth will be necessary for operation. The access route for construction traffic to the northern transitional structure passes through the municipality of Bözberg. The southern transitional structure in the municipality of Villnachern will be located to the south of the SBB railway embankment. The drilling method will be used to construct the SBB railway line underpass.

The costs for the entire project amount to CHF 28 million.

General site plan for the «Gäbihübel» partial underground cabling
General site plan for the «Gäbihübel» partial underground cabling

Cable profile

Systems One system at 380 kilovolts, the other at 220 kilovolts, operated for the service life of 40 years
Dimensions 12 cables laid in parallel
2 parallel systems, each with 2 cables per phase
Cross-section XLPE cable, 2500 mm2, aluminium
Protection Each phase has 2 cables in a separate cable conduit
Weight The cable weight amounts to approx. 21 kilograms per metre

The calculations and forecasts of the grid load have shown that, in the «Strategic Grid 2025», the electrotechnical design of individual grid systems can be redimensioned compared to the previous assumptions. This affects the Beznau – Birr – Mettlen line, amongst others. Analyses on the security of supply have shown that the reserve cable is not required for the «Gäbihübel» partial underground cabling. The insulation of both cable systems is also not yet necessary for 380 kilovolts. One system will be procured for a voltage of 220 kilovolts only and will be operated at this voltage. These cables would have to be replaced to increase the voltage to 380 kilovolts. Swissgrid estimates that the increase in voltage will only take place after the end of the cables' service life. This adjustment allows considerable cost savings to be achieved with regard to the modernisation and demand-driven expansion of the Swiss transmission grid.

Cable trench

Cable trench

During the construction phase, the trench for laying the underground cable is about 25 metres wide. This reduces to around 5 metres during the operating phase. The route with partial underground cabling will be laid in open terrain with a conduit block at a depth of about 2 metres.

Milestones

The construction time is about three years. The existing 220 kilovolt line will be dismantled following commissioning of the new 380 kilovolt line.

30 September 2013 Planning submission
October 2016 Legal planning approval
2017 – 2018 Procurement of the cable and line systems
23 August 2018 Ground-breaking ceremony
End of 2020 Commissioning of the new 380 kilovolt line
2021 Dismantling of the existing 220 kilovolt line

Project advisory council

Every project allows design latitude. When the members of the project advisory council express their opinions candidly, point out options for action and thus make constructive contributions to the discussion, the foundation is laid for applying this design latitude to best effect. In this sense, the project advisory council is a consultative forum in which mutual understanding is promoted and different concerns can be raised directly. This is intended to optimise project communication and increases acceptance.

The project advisory council was deployed up to the completion of the planning approval procedure in 2016. The following persons were members of the project advisory council:

Municipality of Bözberg Heinz Dätwyler, Municipal Councillor
City of Brugg Daniel Moser, Chairman of the Municipality
Municipality of Riniken Daniel Obrist, Vice-Chairman of the Municipality
Municipality of Villnachern Christoph Kamber, Municipal Councillor
Birdlife Aargau Max Gasser
Pro Natura Aargau Dr. Johannes Jenny
WWF Aargau Tonja Zürcher
AKUT Andreas Brack
Landowner, Bözberg Markus Kreis

People & environment

Landscape

Swissgrid will implement the most landscape-friendly line route possible when constructing the Gäbihübel partial underground cabling. Different versions and combinations of the cable route, locations of the transitional structures and the overhead line connections were reviewed. For example, the original position of the northern transitional structure was optimised so that it is concealed by the forest wherever possible. The overhead line connections are sympathetic to the landscape by blending in with the forest skyline.

Electromagnetic fields

An underground line causes electric and magnetic fields just like an overhead line. While electric fields are intercepted by the shielding in the cable, magnetic fields are generated externally. The spatial expansion of the magnetic field is lower than for overhead lines, but the strength directly over the underground cable is much higher than under an overhead line. The limit of 1 microtesla is complied with from a distance of 6 – 8 metres to the line axis of the underground cable, while the corresponding distance for the overhead line is about 60 – 80 metres.

Soil

The «Gäbihübel» partial underground cabling project will allow important knowledge to be gained on the underground cabling of extra-high-voltage lines. Swissgrid is therefore developing a scientific programme in consultation with the competent authorities and departments. The aim is to check the assumptions that were made for the dimensioning of the underground line and involves recording the underground line's impact on the soil. A comparison of the measurements with the calculations allows conclusions to be drawn about the reliability of the assumptions made.

In particular, the following points will be analysed during operation:

Forestry work

Permanent forest clearance (about 4,000 m²) will be carried out for the northern transitional structure, opposite the garage on Bözbergstrasse as well as for the pylon locations. Temporary forest clearance will occur at the location for the northern transitional structure and for the pylon construction sites in the forest (about 17,000 m²). The forestry work will be carried out from the winter of 2017/2018. The reforestation activities for the permanent forest clearance areas will take place in Linn, in the municipality of Bözberg, and in the areas in which pylons are removed.


Downloads


This contact form is sent to new.media@swissgrid.ch

Contact

Title

Please select

Please fill in this field

Please fill in this field

Please enter a valid e-mail address

Please fill in this field

Es gibt im Moment in diese Mannschaft, oh, einige Spieler vergessen ihnen Profi was sie sind. Ich lese nicht sehr viele Zeitungen, aber ich habe gehört viele Situationen. Erstens: wir haben nicht offensiv gespielt. Es gibt keine deutsche Mannschaft spielt offensiv und die Name offensiv wie Bayern. Letzte Spiel hatten wir in Platz drei Spitzen: Elber, Jancka und dann Zickler. Wir müssen nicht vergessen Zickler. Zickler ist eine Spitzen mehr, Mehmet eh mehr Basler. Ist klar diese Wörter, ist möglich verstehen, was ich hab gesagt? Danke. Offensiv, offensiv ist wie machen wir in Platz. Zweitens: ich habe erklärt mit diese zwei Spieler: nach Dortmund brauchen vielleicht Halbzeit Pause. Ich habe auch andere Mannschaften gesehen in Europa nach diese Mittwoch. Ich habe gesehen auch zwei Tage die Training. Ein Trainer ist nicht ein Idiot! Ein Trainer sei sehen was passieren in Platz. In diese Spiel es waren zwei, drei diese Spieler waren schwach wie eine Flasche leer! Haben Sie gesehen Mittwoch, welche Mannschaft hat gespielt Mittwoch? Hat gespielt Mehmet oder gespielt Basler oder hat gespielt Trapattoni? Diese Spieler beklagen mehr als sie spielen! Wissen Sie, warum die Italienmannschaften kaufen nicht diese Spieler? Weil wir haben gesehen viele Male solche Spiel!

This is the error text for the Google reCaptcha which was configured in the component

This contact form is sent to new.media@swissgrid.ch

Contact

Title

Please select

Please fill in this field

Please fill in this field

Please enter a valid e-mail address

Please fill in this field

Es gibt im Moment in diese Mannschaft, oh, einige Spieler vergessen ihnen Profi was sie sind. Ich lese nicht sehr viele Zeitungen, aber ich habe gehört viele Situationen. Erstens: wir haben nicht offensiv gespielt. Es gibt keine deutsche Mannschaft spielt offensiv und die Name offensiv wie Bayern. Letzte Spiel hatten wir in Platz drei Spitzen: Elber, Jancka und dann Zickler. Wir müssen nicht vergessen Zickler. Zickler ist eine Spitzen mehr, Mehmet eh mehr Basler. Ist klar diese Wörter, ist möglich verstehen, was ich hab gesagt? Danke. Offensiv, offensiv ist wie machen wir in Platz. Zweitens: ich habe erklärt mit diese zwei Spieler: nach Dortmund brauchen vielleicht Halbzeit Pause. Ich habe auch andere Mannschaften gesehen in Europa nach diese Mittwoch. Ich habe gesehen auch zwei Tage die Training. Ein Trainer ist nicht ein Idiot! Ein Trainer sei sehen was passieren in Platz. In diese Spiel es waren zwei, drei diese Spieler waren schwach wie eine Flasche leer! Haben Sie gesehen Mittwoch, welche Mannschaft hat gespielt Mittwoch? Hat gespielt Mehmet oder gespielt Basler oder hat gespielt Trapattoni? Diese Spieler beklagen mehr als sie spielen! Wissen Sie, warum die Italienmannschaften kaufen nicht diese Spieler? Weil wir haben gesehen viele Male solche Spiel!

This is the error text for the Google reCaptcha which was configured in the component